Key milestones from 2025 to 2035 and beyond

To meet the challenge PHIGS is addressing, we plan to grow in multiple phases. During the first phase, from 2025 to 2027, PHIGS will build infrastructure, construct 5 family homes, and rent office facilities. PHIGS will hire an executive director, house parents, prior to opening the first homes. At the completion of Phase One, PHIGS will be able to serve 18-20 children. In the second phase, PHIGS will expand to 8 homes and ancillary facilities to expand its program offering to include 24-30 girls and a growing community of house parents, staff and volunteers. Ultimately, PHIGS expects to reach 14 homes serving 42-50 girls beyond 2035 with a team of highly qualified house parents, counselors, and supporting staff.
![]() | PHASE I (2025-2027) | PHASE 2 (2028-2030) | PHASE 3 (2031-2035) |
Land Purchase | $ 500,000 | ||
Development | $ 170,000 | $ 85,000 | $ 78,000 |
Homes Built | $ 2,160,000 (5 homes) | $ 445,000 (1 home) | $ 990,000 (2 homes) |
Chapel | $ 275,000 | ||
Admin / Counseling Building | $ 350,000 | ||
Additional Staff Housing | $ 375,000 | ||
Gymnasium / Aquatics Center | $ 975,000 | ||
TOTAL DEVELOPMENT COST | $ 2,830,000 | $ 2,130,000 | $ 1,443,000 |
TOTAL HOMES IN OPERATION | 5 | 6 | 8 |
# OF GIRLS SERVED | 18-20 | 20-24 | 24-32 |
Phase One:
- Land Purchase - secure 25-35 acres of land by July 1, 2025
- Initial Infrastructure - complete the initial infrastructure development, including all grading, paving, and utilities access points, by November 1, 2025
- First 5 Homes and Staff - construct 5, 4-bedroom, ADA-compliant homes with administrative and house parent staffing by July 1, 2028
Phase Two:
- Extend Infrastructure, construct additional infrastructure for additional Phase Two and Phase Three facilities construction
- 6th Home Completed, construct an additional, 4-bedroom, ADA-compliant home with additional administrative and house parent staffing by July 1, 2029
- Counseling Center, Chapel and Gymnasium/Aquatics Center complex, construct recreational, worship and counseling complex facilities by October 1, 2030
Phase Three:
- 7th & 8th Homes Completed, construct an 2 additional, 4-bedroom, ADA-compliant homes with additional house parent staffing by July 1, 2032
- Additional Staff Housing Completed, construct additional staff housing facility for resident staff and seasonal interns by March 1, 2034
- Major Campus Development Completed, complete campus landscape development and greenway features by October 1, 2035